| WBS |
Name |
Duration |
Start |
Finish |
Actual Start |
Actual Finish |
Resource Names |
| 1 | DEFINE S/W RQMTS | 99.00d | 1/20/97 | 4/28/97 | 1/20/97 | NA | |
| 1.1 | __Software Requirements Specification (SRS) | 99.00d | 1/20/97 | 4/28/97 | 1/20/97 | NA | |
| 1.1.1 | ____Understand Functional & S/W Rqmts | 15.00d | 1/20/97 | 2/3/97 | 1/20/97 | 2/3/97 | |
| 1.1.1.1 | ______Brainstorm Requirements | 8.00d | 1/20/97 | 1/27/97 | 1/20/97 | 1/27/97 | |
| 1.1.1.2 | ______Produce Draft SRS | 8.00d | 1/27/97 | 2/3/97 | 1/27/97 | 2/3/97 | |
| 1.1.2 | ____Clarify stated rqmts | 29.00d | 2/3/97 | 3/3/97 | 2/3/97 | NA | |
| 1.1.2.1 | ______Get feedback from professor | 8.00d | 2/3/97 | 2/10/97 | 2/3/97 | 2/10/97 | |
| 1.1.2.2 | ______Update Requirements Document to reflect comments | 8.00d | 2/10/97 | 2/17/97 | 2/10/97 | 2/17/97 | |
| 1.1.2.3 | ______Get team chop on update | 8.00d | 2/17/97 | 2/24/97 | 2/17/97 | 2/24/97 | |
| 1.1.2.4 | ______Clarify vague and ambiguous requirements | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 1.1.2.5 | ______Assess technology for supplying reqd S/W | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 1.1.3 | ____Baseline SRS | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 1.1.4 | ____Update SRS for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 1.1.5 | ____Update SRS for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 1.1.6 | ____Produce final SRS for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 1.2 | __Software Requirements Process Document | 92.00d | 1/27/97 | 4/28/97 | 1/27/97 | NA | |
| 1.2.1 | ____Produce Draft Rqmts Proc Doc | 8.00d | 1/27/97 | 2/3/97 | 1/27/97 | 2/3/97 | |
| 1.2.2 | ____Update Rqmts Proc Doc for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 1.2.3 | ____Update Rqmts Proc Doc for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 1.2.4 | ____Produce final Rqmts Proc Doc for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 2 | MANAGE PROGRAM RISK | 85.00d | 2/3/97 | 4/28/97 | 2/3/97 | NA | |
| 2.1 | __Risk Mitigation Plan | 85.00d | 2/3/97 | 4/28/97 | 2/3/97 | NA | |
| 2.1.1 | ____Produce Baseline Risk Mitigation Plan | 8.00d | 2/3/97 | 2/10/97 | 2/3/97 | 2/10/97 | |
| 2.1.1.1 | ______Identify Risk Elements, Probabilities and Impacts | 1.00d | 2/3/97 | 2/3/97 | 2/3/97 | 2/3/97 | |
| 2.1.1.2 | ______Produce Draft Risk Mitigation Plan | 5.00d | 2/4/97 | 2/8/97 | 2/4/97 | 2/8/97 | |
| 2.1.1.3 | ______Circulate Risk Mitigation Plan for comment | 3.00d | 2/8/97 | 2/10/97 | 2/8/97 | 2/10/97 | |
| 2.1.1.4 | ______Baseline Risk Mitigation Plan | 1.00d | 2/10/97 | 2/10/97 | 2/10/97 | 2/10/97 | |
| 2.1.2 | ____Update Risk Mitigation Plan for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 2.1.3 | ____Update Risk Mitigation Plan for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 2.1.4 | ____Produce final Risk Mitigation Plan for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 2.2 | __Conduct Risk Mitigation Activities | 50.00d | 2/24/97 | 4/14/97 | NA | NA | |
| 2.2.1 | ____Evaluate Program Risk Elements | 48.00d | 2/24/97 | 4/12/97 | NA | NA | |
| | ____Conduct Risk Mitigation as required | 48.00d | 2/24/97 | 4/12/97 | NA | NA | |
| 2.2.3 | ____Bi-weekly Risk Mitigation Report to PM | 43.00d | 3/3/97 | 4/14/97 | NA | NA | |
| 3 | CONDUCT SOFTWARE CONFIGURATION MGMT | 92.00d | 1/27/97 | 4/28/97 | 1/27/97 | NA | |
| 3.1 | __Produce Requirements Management Plan | 92.00d | 1/27/97 | 4/28/97 | 1/27/97 | NA | |
| 3.1.1 | ____Produce Baseline Rqmts Mgmt Plan | 22.00d | 1/27/97 | 2/17/97 | 1/27/97 | 2/17/97 | |
| 3.1.1.1 | ______Produce Draft Rqmt Mgmt Plan | 8.00d | 1/27/97 | 2/3/97 | 1/27/97 | 2/3/97 | |
| 3.1.1.2 | ______Get feedback from professor | 1.00d | 2/3/97 | 2/3/97 | 2/3/97 | 2/3/97 | |
| 3.1.1.3 | ______Baseline Rqmts Mgmt Plan | 8.00d | 2/10/97 | 2/17/97 | 2/10/97 | 2/17/97 | |
| 3.1.2 | ____Update Rqmts Mgmt Plan for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 3.1.3 | ____Update Rqmts Mgmt Plan for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 3.1.4 | ____Produce final Rqmts Mgmt Plan for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 3.2 | __Produce Software Configuration Management Plan (SCMP) | 64.00d | 2/24/97 | 4/28/97 | NA | NA | |
| 3.2.1 | ____Produce Baseline Config Mgmt Plan | 22.00d | 2/24/97 | 3/17/97 | NA | NA | |
| 3.2.1.1 | ______Produce Draft SCMP | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 3.2.1.2 | ______Get feedback from professor | 1.00d | 3/17/97 | 3/17/97 | NA | NA | |
| 3.2.2 | ____Update SCMP for Preliminary Design Review (Baseline) | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 3.2.3 | ____Update SCMP for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 3.2.4 | ____Produce final SCMP for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 3.3 | __Conduct Configuration Management Activities | 78.00d | 2/10/97 | 4/28/97 | NA | NA | |
| 3.3.1 | ____Enter Baseline Documentation into Configuration Control | 78.00d | 2/10/97 | 4/28/97 | NA | NA | |
| 3.3.1.1 | ______Enter SRS into Configuration Control | 1.00d | 2/17/97 | 2/17/97 | NA | NA | |
| 3.3.1.2 | ______Enter S/W Rqmts Proc Doc into Configuration Control | 1.00d | 3/24/97 | 3/24/97 | NA | NA | |
| 3.3.1.3 | ______Enter Risk Mitigation Plan into Configuration Control | 1.00d | 2/10/97 | 2/10/97 | NA | NA | |
| 3.3.1.4 | ______Enter S/W Rqmts Mgmt Plan into Configuration Control | 1.00d | 2/17/97 | 2/17/97 | NA | NA | |
| 3.3.1.5 | ______Enter SCMP into Configuration Control | 1.00d | 3/24/97 | 3/24/97 | NA | NA | |
| 3.3.1.6 | ______Enter QA/Test Plan into Configuration Control | 1.00d | 3/24/97 | 3/24/97 | NA | NA | |
| 3.3.1.7 | ______Enter Software Test Report into Configuration Control | 1.00d | 4/28/97 | 4/28/97 | NA | NA | |
| 3.3.2 | ____Update Documentation Baseline for PDR | 1.00d | 3/24/97 | 3/24/97 | NA | NA | |
| 3.3.3 | ____Update Documentation Baseline for CDR | 1.00d | 4/7/97 | 4/7/97 | NA | NA | |
| 3.3.4 | ____Update Documentation Baseline for FAT | 1.00d | 4/28/97 | 4/28/97 | NA | NA | |
| 3.3.5 | ____Enter Initial Software Baseline into Configuration Control | 1.00d | 2/24/97 | 2/24/97 | NA | NA | |
| 3.3.6 | ____Enter Build 2 into Configuration Control | 1.00d | 3/17/97 | 3/17/97 | NA | NA | |
| 3.3.7 | ____Enter Build 3 into Configuration Control | 1.00d | 3/31/97 | 3/31/97 | NA | NA | |
| 3.3.8 | ____Enter Final Build into Configuration Control | 1.00d | 4/13/97 | 4/13/97 | NA | NA | |
| 3.3.9 | ____Bi-weekly Configuration Mgmt Report to PM | 43.00d | 3/3/97 | 4/14/97 | NA | NA | |
| 4 | DEVELOP S/W ARCHITECTURE | 92.00d | 1/27/97 | 4/28/97 | 1/27/97 | NA | |
| 4.1 | __Produce Software Design Document | 8.00d | 2/17/97 | 2/24/97 | 2/17/97 | 2/24/97 | |
| 4.2 | __Update Software Design Document for PDR | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 4.3 | __Update Software Design Document for CDR | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 4.4 | __Produce Final Software Design Document | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 4.5 | __Deliver Initial Software Build | 29.00d | 1/27/97 | 2/24/97 | 1/27/97 | NA | |
| 4.5.1 | ____Prototype Links to Software Program Management Sites | 28.00d | 1/27/97 | 2/23/97 | 1/27/97 | 2/23/97 | |
| 4.5.2 | ____Prototype Team Review Section | 28.00d | 1/27/97 | 2/23/97 | 1/27/97 | 2/23/97 | |
| 4.5.3 | ____Deliver Initial Build to Software Test | 1.00d | 2/24/97 | 2/24/97 | NA | NA | |
| 4.6 | __Deliver 2nd Software Build | 22.00d | 2/24/97 | 3/17/97 | NA | NA | |
| 4.6.1 | ____Develop WWW Site Layout | 21.00d | 2/24/97 | 3/16/97 | NA | NA | |
| 4.6.2 | ____Develop "chat room" capability | 21.00d | 2/24/97 | 3/16/97 | NA | NA | |
| 4.6.3 | ____Develop a minimum of 10 Links to other web sites | 21.00d | 2/24/97 | 3/16/97 | NA | NA | |
| 4.6.4 | ____Develop section of introductory material | 21.00d | 2/24/97 | 3/16/97 | NA | NA | |
| 4.6.5 | ____Develop list of suggested keywords and links to other web search engines | 21.00d | 2/24/97 | 3/16/97 | NA | NA | |
| 4.6.6 | ____Deliver Build 2 to Software Test | 1.00d | 3/17/97 | 3/17/97 | NA | NA | |
| 4.7 | __Deliver 3rd Software Build | 15.00d | 3/17/97 | 3/31/97 | NA | NA | |
| 4.7.1 | ____Develop list of or links to a minimum of five tool descriptions | 14.00d | 3/17/97 | 3/30/97 | NA | NA | |
| 4.7.2 | ____Develop a "levity" page | 14.00d | 3/17/97 | 3/30/97 | NA | NA | |
| 4.7.3 | ____Deliver Build 3 to Software Test | 1.00d | 3/31/97 | 3/31/97 | NA | NA | |
| 4.8 | __Deliver Final Software Build | 15.00d | 3/31/97 | 4/14/97 | NA | NA | |
| 4.8.1 | ____Develop unique materials section for MJY Team papers | 14.00d | 3/31/97 | 4/13/97 | NA | NA | |
| 4.8.2 | ____Develop bibliography of publications of interest | 14.00d | 3/31/97 | 4/13/97 | NA | NA | |
| 4.8.3 | ____Develop a "lessons learned" page | 14.00d | 3/31/97 | 4/13/97 | NA | NA | |
| 4.8.4 | ____Deliver Final Build to Software Test | 1.00d | 4/14/97 | 4/14/97 | NA | NA | |
| 5 | CONDUCT SOFTWARE QA/TEST | 65.00d | 2/24/97 | 4/29/97 | NA | NA | |
| 5.1 | __Produce QA/Test Plan | 64.00d | 2/24/97 | 4/28/97 | NA | NA | |
| 5.1.1 | ____Produce Baseline QA/Test Plan | 22.00d | 2/24/97 | 3/17/97 | NA | NA | |
| 5.1.1.1 | ______Produce Draft QA/Test Plan | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 5.1.1.2 | ______Get feedback from professor | 1.00d | 3/17/97 | 3/17/97 | NA | NA | |
| 5.1.2 | ____Update QA/Test Plan for Preliminary Design Review (Baseline) | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 5.1.3 | ____Update QA/Test Plan for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 5.1.4 | ____Produce final QA/Test Plan for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 5.2 | __Conduct Software Test | 56.00d | 2/25/97 | 4/21/97 | NA | NA | |
| 5.2.1 | ____Test Initial Software Build | 8.00d | 2/25/97 | 3/4/97 | NA | NA | |
| 5.2.1.1 | ______Conduct Initial Build Test | 7.00d | 2/25/97 | 3/3/97 | NA | NA | |
| 5.2.1.2 | ______Provide Test Status to PM, Developer | 1.00d | 3/4/97 | 3/4/97 | NA | NA | |
| 5.2.2 | ____Test Build 2 | 8.00d | 3/18/97 | 3/25/97 | NA | NA | |
| 5.2.2.1 | ______Conduct Build 2 Test | 7.00d | 3/18/97 | 3/24/97 | NA | NA | |
| 5.2.2.2 | ______Provide Test Status to PM, Developer | 1.00d | 3/25/97 | 3/25/97 | NA | NA | |
| 5.2.3 | ____Test Build 3 | 8.00d | 4/1/97 | 4/8/97 | NA | NA | |
| 5.2.3.1 | ______Conduct Build 3 Test | 7.00d | 4/1/97 | 4/7/97 | NA | NA | |
| 5.2.3.2 | ______Provide Test Status to PM, Developer | 1.00d | 4/8/97 | 4/8/97 | NA | NA | |
| 5.2.4 | ____Test Final Build | 7.00d | 4/15/97 | 4/21/97 | NA | NA | |
| 5.3 | __Produce Software Test Report | 8.00d | 4/22/97 | 4/29/97 | NA | NA | |
| 5.3.1 | ____Compile Software Test Results | 7.00d | 4/22/97 | 4/28/97 | NA | NA | |
| 5.3.2 | ____Deliver Software Test Report | 1.00d | 4/29/97 | 4/29/97 | NA | NA | |
| 6 | PERFORM PROJECT MGMT FUNCTIONS | 99.00d | 1/27/97 | 5/5/97 | 1/27/97 | NA | |
| 6.1 | __DEFINE PROJECT GOALS & OBJECTIVES | 8.00d | 1/27/97 | 2/3/97 | 1/27/97 | 2/3/97 | |
| 6.2 | __SCOPE AND PLAN THE PROJECT | 20.00d | 2/12/97 | 3/3/97 | 2/12/97 | NA | |
| 6.2.1 | ____Define S/W Project Mgmt Process | 6.00d | 2/12/97 | 2/17/97 | 2/12/97 | 2/17/97 | |
| 6.2.2 | ____Define Work Breakdown Structure (WBS) | 6.00d | 2/19/97 | 2/24/97 | 2/19/97 | 2/24/97 | |
| 6.2.3 | ____Determine Project Schedule | 6.00d | 2/19/97 | 2/24/97 | 2/19/97 | 2/24/97 | |
| 6.2.4 | ____Produce MS Project Plan | 6.00d | 2/19/97 | 2/24/97 | 2/19/97 | 2/24/97 | |
| 6.2.5 | ____Produce S/W Project Mgmt Plan (SPMP) | 6.00d | 2/19/97 | 2/24/97 | 2/19/97 | 2/24/97 | |
| 6.2.6 | ____Assign Resources to Tasks | 7.00d | 2/25/97 | 3/3/97 | NA | NA | |
| 6.3 | __Administrate the implementation | 56.00d | 2/24/97 | 4/20/97 | NA | NA | |
| 6.3.1 | ____Collect weekly actuals for task completion | 50.00d | 2/24/97 | 4/14/97 | NA | NA | |
| 6.3.2 | ____Update MS Project Plan | 55.00d | 2/25/97 | 4/20/97 | NA | NA | |
| 6.4 | __Evaluate performance and product | 49.00d | 2/25/97 | 4/14/97 | NA | NA | |
| 6.4.1 | ____Conduct bi-weekly project reviews | 49.00d | 2/25/97 | 4/14/97 | NA | NA | |
| 6.4.1.1 | ______Evaluate actual versus projected schedule | 48.00d | 2/25/97 | 4/13/97 | NA | NA | |
| 6.4.1.2 | ______Evaluate actual versus projected cost | 48.00d | 2/25/97 | 4/13/97 | NA | NA | |
| 6.4.1.3 | ______Prepare bi-weekly report | 48.00d | 2/25/97 | 4/13/97 | NA | NA | |
| 6.4.1.4 | ______Brief bi-weekly report to PM | 43.00d | 3/3/97 | 4/14/97 | NA | NA | |
| 6.5 | __Report Status to Customer/Class | 36.00d | 3/17/97 | 4/21/97 | NA | NA | |
| 6.5.1 | ____Status Report 1 (Mar 24) | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 6.5.1.1 | ______Prepare Status Report | 7.00d | 3/17/97 | 3/23/97 | NA | NA | |
| 6.5.1.2 | ______Brief Status Report | 1.00d | 3/24/97 | 3/24/97 | NA | NA | |
| 6.5.2 | ____Status Report 2 (Apr 7) | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 6.5.2.1 | ______Prepare Status Report | 7.00d | 3/31/97 | 4/6/97 | NA | NA | |
| 6.5.2.2 | ______Brief Status Report | 1.00d | 4/7/97 | 4/7/97 | NA | NA | |
| 6.5.3 | ____Status Report 3 (Apr 21) | 8.00d | 4/14/97 | 4/21/97 | NA | NA | |
| 6.5.3.1 | ______Prepare Status Report | 7.00d | 4/14/97 | 4/20/97 | NA | NA | |
| 6.5.3.2 | ______Brief Status Report | 1.00d | 4/21/97 | 4/21/97 | NA | NA | |
| 6.6 | __Terminate the Project | 1.00d | 5/5/97 | 5/5/97 | NA | NA | |
| 6.6.1 | ____Provide Final Documentation to Dr. Bechtold | 1.00d | 5/5/97 | 5/5/97 | NA | NA | |
| 6.6.2 | ____Provide Web Site Code to Dr. Bechtold | 1.00d | 5/5/97 | 5/5/97 | NA | NA | |