WBS.24.FEB.97
24 February 1997

MJY Team Schedule v. 1.0


MJY Project Schedule

WBS Name Duration Start Finish Actual Start Actual Finish Resource Names
1DEFINE S/W RQMTS99.00d1/20/974/28/971/20/97NA
1.1__Software Requirements Specification (SRS)99.00d1/20/974/28/971/20/97NA
1.1.1____Understand Functional & S/W Rqmts15.00d1/20/972/3/971/20/972/3/97
1.1.1.1______Brainstorm Requirements8.00d1/20/971/27/971/20/971/27/97
1.1.1.2______Produce Draft SRS8.00d1/27/972/3/971/27/972/3/97
1.1.2____Clarify stated rqmts29.00d2/3/973/3/972/3/97NA
1.1.2.1______Get feedback from professor8.00d2/3/972/10/972/3/972/10/97
1.1.2.2______Update Requirements Document to reflect comments8.00d2/10/972/17/972/10/972/17/97
1.1.2.3______Get team chop on update8.00d2/17/972/24/972/17/972/24/97
1.1.2.4______Clarify vague and ambiguous requirements8.00d2/24/973/3/97NANA
1.1.2.5______Assess technology for supplying reqd S/W8.00d2/24/973/3/97NANA
1.1.3____Baseline SRS8.00d2/24/973/3/97NANA
1.1.4____Update SRS for Preliminary Design Review8.00d3/17/973/24/97NANA
1.1.5____Update SRS for Critical Design Review8.00d3/31/974/7/97NANA
1.1.6____Produce final SRS for Functional Acceptance Testing8.00d4/21/974/28/97NANA
1.2__Software Requirements Process Document92.00d1/27/974/28/971/27/97NA
1.2.1____Produce Draft Rqmts Proc Doc8.00d1/27/972/3/971/27/972/3/97
1.2.2____Update Rqmts Proc Doc for Preliminary Design Review8.00d3/17/973/24/97NANA
1.2.3____Update Rqmts Proc Doc for Critical Design Review8.00d3/31/974/7/97NANA
1.2.4____Produce final Rqmts Proc Doc for Functional Acceptance Testing8.00d4/21/974/28/97NANA
2MANAGE PROGRAM RISK85.00d2/3/974/28/972/3/97NA
2.1__Risk Mitigation Plan85.00d2/3/974/28/972/3/97NA
2.1.1____Produce Baseline Risk Mitigation Plan8.00d2/3/972/10/972/3/972/10/97
2.1.1.1______Identify Risk Elements, Probabilities and Impacts1.00d2/3/972/3/972/3/972/3/97
2.1.1.2______Produce Draft Risk Mitigation Plan5.00d2/4/972/8/972/4/972/8/97
2.1.1.3______Circulate Risk Mitigation Plan for comment3.00d2/8/972/10/972/8/972/10/97
2.1.1.4______Baseline Risk Mitigation Plan1.00d2/10/972/10/972/10/972/10/97
2.1.2____Update Risk Mitigation Plan for Preliminary Design Review8.00d3/17/973/24/97NANA
2.1.3____Update Risk Mitigation Plan for Critical Design Review8.00d3/31/974/7/97NANA
2.1.4____Produce final Risk Mitigation Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
2.2__Conduct Risk Mitigation Activities50.00d2/24/974/14/97NANA
2.2.1____Evaluate Program Risk Elements48.00d2/24/974/12/97NANA
____Conduct Risk Mitigation as required48.00d2/24/974/12/97NANA
2.2.3____Bi-weekly Risk Mitigation Report to PM43.00d3/3/974/14/97NANA
3CONDUCT SOFTWARE CONFIGURATION MGMT92.00d1/27/974/28/971/27/97NA
3.1__Produce Requirements Management Plan92.00d1/27/974/28/971/27/97NA
3.1.1____Produce Baseline Rqmts Mgmt Plan22.00d1/27/972/17/971/27/972/17/97
3.1.1.1______Produce Draft Rqmt Mgmt Plan8.00d1/27/972/3/971/27/972/3/97
3.1.1.2______Get feedback from professor1.00d2/3/972/3/972/3/972/3/97
3.1.1.3______Baseline Rqmts Mgmt Plan8.00d2/10/972/17/972/10/972/17/97
3.1.2____Update Rqmts Mgmt Plan for Preliminary Design Review8.00d3/17/973/24/97NANA
3.1.3____Update Rqmts Mgmt Plan for Critical Design Review8.00d3/31/974/7/97NANA
3.1.4____Produce final Rqmts Mgmt Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
3.2__Produce Software Configuration Management Plan (SCMP)64.00d2/24/974/28/97NANA
3.2.1____Produce Baseline Config Mgmt Plan22.00d2/24/973/17/97NANA
3.2.1.1______Produce Draft SCMP8.00d2/24/973/3/97NANA
3.2.1.2______Get feedback from professor1.00d3/17/973/17/97NANA
3.2.2____Update SCMP for Preliminary Design Review (Baseline)8.00d3/17/973/24/97NANA
3.2.3____Update SCMP for Critical Design Review8.00d3/31/974/7/97NANA
3.2.4____Produce final SCMP for Functional Acceptance Testing8.00d4/21/974/28/97NANA
3.3__Conduct Configuration Management Activities78.00d2/10/974/28/97NANA
3.3.1____Enter Baseline Documentation into Configuration Control78.00d2/10/974/28/97NANA
3.3.1.1______Enter SRS into Configuration Control1.00d2/17/972/17/97NANA
3.3.1.2______Enter S/W Rqmts Proc Doc into Configuration Control1.00d3/24/973/24/97NANA
3.3.1.3______Enter Risk Mitigation Plan into Configuration Control1.00d2/10/972/10/97NANA
3.3.1.4______Enter S/W Rqmts Mgmt Plan into Configuration Control1.00d2/17/972/17/97NANA
3.3.1.5______Enter SCMP into Configuration Control1.00d3/24/973/24/97NANA
3.3.1.6______Enter QA/Test Plan into Configuration Control1.00d3/24/973/24/97NANA
3.3.1.7______Enter Software Test Report into Configuration Control1.00d4/28/974/28/97NANA
3.3.2____Update Documentation Baseline for PDR1.00d3/24/973/24/97NANA
3.3.3____Update Documentation Baseline for CDR1.00d4/7/974/7/97NANA
3.3.4____Update Documentation Baseline for FAT1.00d4/28/974/28/97NANA
3.3.5____Enter Initial Software Baseline into Configuration Control1.00d2/24/972/24/97NANA
3.3.6____Enter Build 2 into Configuration Control1.00d3/17/973/17/97NANA
3.3.7____Enter Build 3 into Configuration Control1.00d3/31/973/31/97NANA
3.3.8____Enter Final Build into Configuration Control1.00d4/13/974/13/97NANA
3.3.9____Bi-weekly Configuration Mgmt Report to PM43.00d3/3/974/14/97NANA
4DEVELOP S/W ARCHITECTURE92.00d1/27/974/28/971/27/97NA
4.1__Produce Software Design Document8.00d2/17/972/24/972/17/972/24/97
4.2__Update Software Design Document for PDR8.00d3/17/973/24/97NANA
4.3__Update Software Design Document for CDR8.00d3/31/974/7/97NANA
4.4__Produce Final Software Design Document8.00d4/21/974/28/97NANA
4.5__Deliver Initial Software Build29.00d1/27/972/24/971/27/97NA
4.5.1____Prototype Links to Software Program Management Sites28.00d1/27/972/23/971/27/972/23/97
4.5.2____Prototype Team Review Section28.00d1/27/972/23/971/27/972/23/97
4.5.3____Deliver Initial Build to Software Test1.00d2/24/972/24/97NANA
4.6__Deliver 2nd Software Build22.00d2/24/973/17/97NANA
4.6.1____Develop WWW Site Layout21.00d2/24/973/16/97NANA
4.6.2____Develop "chat room" capability21.00d2/24/973/16/97NANA
4.6.3____Develop a minimum of 10 Links to other web sites21.00d2/24/973/16/97NANA
4.6.4____Develop section of introductory material21.00d2/24/973/16/97NANA
4.6.5____Develop list of suggested keywords and links to other web search engines21.00d2/24/973/16/97NANA
4.6.6____Deliver Build 2 to Software Test1.00d3/17/973/17/97NANA
4.7__Deliver 3rd Software Build15.00d3/17/973/31/97NANA
4.7.1____Develop list of or links to a minimum of five tool descriptions14.00d3/17/973/30/97NANA
4.7.2____Develop a "levity" page14.00d3/17/973/30/97NANA
4.7.3____Deliver Build 3 to Software Test1.00d3/31/973/31/97NANA
4.8__Deliver Final Software Build15.00d3/31/974/14/97NANA
4.8.1____Develop unique materials section for MJY Team papers14.00d3/31/974/13/97NANA
4.8.2____Develop bibliography of publications of interest14.00d3/31/974/13/97NANA
4.8.3____Develop a "lessons learned" page14.00d3/31/974/13/97NANA
4.8.4____Deliver Final Build to Software Test1.00d4/14/974/14/97NANA
5CONDUCT SOFTWARE QA/TEST65.00d2/24/974/29/97NANA
5.1__Produce QA/Test Plan64.00d2/24/974/28/97NANA
5.1.1____Produce Baseline QA/Test Plan22.00d2/24/973/17/97NANA
5.1.1.1______Produce Draft QA/Test Plan8.00d2/24/973/3/97NANA
5.1.1.2______Get feedback from professor1.00d3/17/973/17/97NANA
5.1.2____Update QA/Test Plan for Preliminary Design Review (Baseline)8.00d3/17/973/24/97NANA
5.1.3____Update QA/Test Plan for Critical Design Review8.00d3/31/974/7/97NANA
5.1.4____Produce final QA/Test Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
5.2__Conduct Software Test56.00d2/25/974/21/97NANA
5.2.1____Test Initial Software Build8.00d2/25/973/4/97NANA
5.2.1.1______Conduct Initial Build Test7.00d2/25/973/3/97NANA
5.2.1.2______Provide Test Status to PM, Developer1.00d3/4/973/4/97NANA
5.2.2____Test Build 28.00d3/18/973/25/97NANA
5.2.2.1______Conduct Build 2 Test7.00d3/18/973/24/97NANA
5.2.2.2______Provide Test Status to PM, Developer1.00d3/25/973/25/97NANA
5.2.3____Test Build 38.00d4/1/974/8/97NANA
5.2.3.1______Conduct Build 3 Test7.00d4/1/974/7/97NANA
5.2.3.2______Provide Test Status to PM, Developer1.00d4/8/974/8/97NANA
5.2.4____Test Final Build7.00d4/15/974/21/97NANA
5.3__Produce Software Test Report8.00d4/22/974/29/97NANA
5.3.1____Compile Software Test Results7.00d4/22/974/28/97NANA
5.3.2____Deliver Software Test Report1.00d4/29/974/29/97NANA
6PERFORM PROJECT MGMT FUNCTIONS99.00d1/27/975/5/971/27/97NA
6.1__DEFINE PROJECT GOALS & OBJECTIVES8.00d1/27/972/3/971/27/972/3/97
6.2__SCOPE AND PLAN THE PROJECT20.00d2/12/973/3/972/12/97NA
6.2.1____Define S/W Project Mgmt Process6.00d2/12/972/17/972/12/972/17/97
6.2.2____Define Work Breakdown Structure (WBS)6.00d2/19/972/24/972/19/972/24/97
6.2.3____Determine Project Schedule6.00d2/19/972/24/972/19/972/24/97
6.2.4____Produce MS Project Plan6.00d2/19/972/24/972/19/972/24/97
6.2.5____Produce S/W Project Mgmt Plan (SPMP)6.00d2/19/972/24/972/19/972/24/97
6.2.6____Assign Resources to Tasks7.00d2/25/973/3/97NANA
6.3__Administrate the implementation56.00d2/24/974/20/97NANA
6.3.1____Collect weekly actuals for task completion50.00d2/24/974/14/97NANA
6.3.2____Update MS Project Plan55.00d2/25/974/20/97NANA
6.4__Evaluate performance and product49.00d2/25/974/14/97NANA
6.4.1____Conduct bi-weekly project reviews49.00d2/25/974/14/97NANA
6.4.1.1______Evaluate actual versus projected schedule48.00d2/25/974/13/97NANA
6.4.1.2______Evaluate actual versus projected cost48.00d2/25/974/13/97NANA
6.4.1.3______Prepare bi-weekly report48.00d2/25/974/13/97NANA
6.4.1.4______Brief bi-weekly report to PM43.00d3/3/974/14/97NANA
6.5__Report Status to Customer/Class36.00d3/17/974/21/97NANA
6.5.1____Status Report 1 (Mar 24)8.00d3/17/973/24/97NANA
6.5.1.1______Prepare Status Report7.00d3/17/973/23/97NANA
6.5.1.2______Brief Status Report1.00d3/24/973/24/97NANA
6.5.2____Status Report 2 (Apr 7)8.00d3/31/974/7/97NANA
6.5.2.1______Prepare Status Report7.00d3/31/974/6/97NANA
6.5.2.2______Brief Status Report1.00d4/7/974/7/97NANA
6.5.3____Status Report 3 (Apr 21)8.00d4/14/974/21/97NANA
6.5.3.1______Prepare Status Report7.00d4/14/974/20/97NANA
6.5.3.2______Brief Status Report1.00d4/21/974/21/97NANA
6.6__Terminate the Project1.00d5/5/975/5/97NANA
6.6.1____Provide Final Documentation to Dr. Bechtold1.00d5/5/975/5/97NANA
6.6.2____Provide Web Site Code to Dr. Bechtold1.00d5/5/975/5/97NANA


Software Project Management / Comments? / Back / Last Updated: April 7, 1997