WBS.22.FEB.97
22 February 1997

MJY Team Schedule v. 0.1


MJY Project Schedule

WBS Name Duration Start Finish Actual Start Actual Finish Resource Names
1DEFINE S/W RQMTS99.00d1/20/974/28/971/20/97NA
1.1__Understand Functional & S/W Rqmts15.00d1/20/972/3/971/20/972/3/97
1.1.1____Brainstorm Requirements8.00d1/20/971/27/971/20/971/27/97
1.1.2____Produce Draft Requirements Document8.00d1/27/972/3/971/27/972/3/97
1.2__Clarify stated rqmts29.00d2/3/973/3/972/3/97NA
1.2.1____Get feedback from professor8.00d2/3/972/10/972/3/972/10/97
1.2.2____Update Requirements Document to reflect comments8.00d2/10/972/17/972/10/972/17/97
1.2.3____Get team chop on update8.00d2/17/972/24/97NANA
1.2.4____Clarify vague and ambiguous requirements8.00d2/24/973/3/97NANA
1.2.5____Assess technology for supplying reqd S/W8.00d2/24/973/3/97NANA
1.2.6____Baseline Requirements Document8.00d2/24/973/3/97NANA
1.3__Software Requirements Process Document57.00d1/27/973/24/971/27/97NA
1.3.1____Produce Draft Requirements Process Document8.00d1/27/972/3/971/27/972/3/97
1.3.2____Baseline Requirements Process Document8.00d3/17/973/24/97NANA
1.4__Update SRS for Preliminary Design Review8.00d3/17/973/24/97NANA
1.5__Update SRS for Critical Design Review8.00d3/31/974/7/97NANA
1.6__Produce final SRS for Functional Acceptance Testing8.00d4/21/974/28/97NANA
2MANAGE PROGRAM RISK22.00d1/20/972/10/972/3/97NA
2.1__Produce Draft Risk Mitigation Plan (RMP)8.00d2/3/972/10/972/3/972/10/97
2.1.1____Identify Risk Elements, Probabilities and Impacts1.00d2/3/972/3/972/3/972/3/97
2.1.2____Produce Draft RMP5.00d2/4/972/8/972/4/972/8/97
2.1.3____Circulate RMP for comment3.00d2/8/972/10/972/8/972/10/97
2.1.4____Baseline RMP1.00d2/10/972/10/972/10/972/10/97
2.2__Conduct Risk Mitigation Activities1.00d1/20/971/20/97NANA
2.2.1____Risk Monitoring Program1.00d1/20/971/20/97NANA
2.2.2____Bi-weekly Risk Mitigation Report1.00d1/20/971/20/97NANA
2.3__Update RMP for Preliminary Design Review1.00d1/20/971/20/97NANA
2.4__Update RMP for Critical Design Review1.00d1/20/971/20/97NANA
2.5__Produce final RMP for Functional Acceptance Testing1.00d1/20/971/20/97NANA
3CONDUCT SOFTWARE CONFIGURATION MGMT92.00d1/27/974/28/971/27/97NA
3.1__Produce Requirements Management Plan (RMP)22.00d1/27/972/17/971/27/972/17/97
3.1.1____Produce Draft Rqmts Mgmt Plan8.00d1/27/972/3/971/27/972/3/97
3.1.2____Get feedback from professor8.00d2/3/972/10/972/3/972/10/97
3.1.3____Update Baseline Rqmts Mgmt Plan8.00d2/10/972/17/972/10/972/17/97
3.2__Update Rqmts Mgmt Plan for Preliminary Design Review8.00d3/17/973/24/97NANA
3.3__Update Rqmts Mgmt Plan for Critical Design Review8.00d3/31/974/7/97NANA
3.4__Produce final Rqmts Mgmt Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
4Produce Configuration Management Plan (CMP)29.00d2/24/973/24/97NANA
4.1__Produce Draft Config Mgmt Plan8.00d2/24/973/3/97NANA
4.2__Get feedback from professor1.00d3/17/973/17/97NANA
4.3__Update Config Mgmt Plan8.00d3/17/973/24/97NANA
5Update Config Mgmt Plan for Preliminary Design Review8.00d3/17/973/24/97NANA
6Update Config Mgmt Plan for Critical Design Review8.00d3/31/974/7/97NANA
7Produce final Config Mgmt Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
8Conduct Configuration Management Activities1.00d1/20/971/20/97NANA
8.1__Configuration Management Activities1.00d1/20/971/20/97NANA
8.2__Bi-weekly Configuration Management Report1.00d1/20/971/20/97NANA
9CONDUCT SOFTWARE QA/TEST99.00d1/20/974/28/97NANA
9.1__Produce Quality Assurance Plan64.00d2/24/974/28/97NANA
9.1.1____Produce draft Quality Assurance Plan8.00d2/24/973/3/97NANA
9.1.2____Get feedback from professor1.00d3/17/973/17/97NANA
9.1.3____Update Baseline QA Plan8.00d3/17/973/24/97NANA
9.1.4____Update QA/Test Plan for Preliminary Design Review8.00d3/17/973/24/97NANA
9.1.5____Update QA/Test Plan for Critical Design Review8.00d3/31/974/7/97NANA
9.1.6____Produce final QA/Test Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
9.2__Conduct Software Test1.00d1/20/971/20/97NANA
9.3__Produce Software Test Report1.00d1/20/971/20/97NANA
10Produce Configuration Management Plan (CMP)29.00d2/24/973/24/97NANA
10.1__Produce Draft Config Mgmt Plan8.00d2/24/973/3/97NANA
10.2__Get feedback from professor1.00d3/17/973/17/97NANA
10.3__Update Config Mgmt Plan8.00d3/17/973/24/97NANA
11Update Config Mgmt Plan for Preliminary Design Review8.00d3/17/973/24/97NANA
12Update Config Mgmt Plan for Critical Design Review8.00d3/31/974/7/97NANA
13Produce final Config Mgmt Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
14Conduct Configuration Management Activities1.00d1/20/971/20/97NANA
14.1__Configuration Management Activities1.00d1/20/971/20/97NANA
14.2__Bi-weekly Configuration Management Report1.00d1/20/971/20/97NANA
15DEVELOP S/W ARCHITECTURE36.00d1/20/972/24/97NANA
15.1__Produce Software Design Document8.00d2/17/972/24/97NANA
15.2__Update Software Design Document for PDR1.00d1/20/971/20/97NANA
15.3__Update Software Design Document for CDR1.00d1/20/971/20/97NANA
15.4__Produce Final Software Design Document1.00d1/20/971/20/97NANA
15.5__Deliver Initial Software Build1.00d1/20/971/20/97NANA
15.5.1____Prototype Links to Software Program Management Sites1.00d1/20/971/20/97NANA
15.5.2____Prototype Team Review Section1.00d1/20/971/20/97NANA
15.6__Deliver 2nd Software Build1.00d1/20/971/20/97NANA
15.6.1____Develop WWW Site Layout1.00d1/20/971/20/97NANA
15.6.2____Develop "chat room" capability1.00d1/20/971/20/97NANA
15.6.3____Develop a minimum of 10 Links to other web sites1.00d1/20/971/20/97NANA
15.6.4____Develop section of introductory material1.00d1/20/971/20/97NANA
15.6.5____Develop list of suggested keywords and links to other web search engines1.00d1/20/971/20/97NANA
15.7__Deliver 3rd Software Build1.00d1/20/971/20/97NANA
15.7.1____Develop list of or links to a minimum of five tool descriptions1.00d1/20/971/20/97NANA
15.7.2____Develop a "levity" page1.00d1/20/971/20/97NANA
15.8__Deliver Final Software Build1.00d1/20/971/20/97NANA
15.8.1____Develop unique materials section for MJY Team papers1.00d1/20/971/20/97NANA
15.8.2____Develop bibliography of publications of interest1.00d1/20/971/20/97NANA
15.8.3____Develop a "lessons learned" page1.00d1/20/971/20/97NANA
16DEVELOP EXTERNAL FUNCTIONAL SPECIFICATION1.00d1/20/971/20/97NANA
17PRODUCE AND DELIVER S/W ITEMS1.00d1/20/971/20/97NANA
18PERFORM PROJECT MGMT FUNCTIONS91.00d1/20/974/20/972/12/97NA
18.1__DEFINE PROJECT GOALS & OBJECTIVES1.00d1/20/971/20/97NANA
18.2__SCOPE AND PLAN THE PROJECT13.00d2/12/972/24/972/12/97NA
18.2.1____Define S/W Project Mgmt Process6.00d2/12/972/17/972/12/972/17/97
18.2.2____Define Work Breakdown Structure (WBS)6.00d2/19/972/24/97NANA
18.2.3____Determine Project Schedule6.00d2/19/972/24/97NANA
18.2.4____Assign Resources to Tasks6.00d2/19/972/24/97NANA
18.2.5____Produce MS Project Plan6.00d2/19/972/24/97NANA
18.2.6____Produce S/W Project Mgmt Plan (SPMP)6.00d2/19/972/24/97NANA
18.3__Administrate the implementation56.00d2/24/974/20/97NANA
18.3.1____Collect weekly actuals for task completion50.00d2/24/974/14/97NANA
18.3.2____Update MS Project Plan55.00d2/25/974/20/97NANA
18.4__Evaluate performance and product49.00d2/25/974/14/97NANA
18.4.1____Conduct bi-weekly project reviews49.00d2/25/974/14/97NANA
18.4.1.1______Evaluate actual versus projected schedule48.00d2/25/974/13/97NANA
18.4.1.2______Evaluate actual versus projected cost48.00d2/25/974/13/97NANA
18.4.1.3______Prepare bi-weekly report48.00d2/25/974/13/97NANA
18.4.1.4______Brief weekly report43.00d3/3/974/14/97NANA


Software Project Management / Comments? / Back / Last Updated: April 7, 1997