| WBS |
Name |
Duration |
Start |
Finish |
Actual Start |
Actual Finish |
Resource Names |
| 1 | DEFINE S/W RQMTS | 99.00d | 1/20/97 | 4/28/97 | 1/20/97 | NA | |
| 1.1 | __Understand Functional & S/W Rqmts | 15.00d | 1/20/97 | 2/3/97 | 1/20/97 | 2/3/97 | |
| 1.1.1 | ____Brainstorm Requirements | 8.00d | 1/20/97 | 1/27/97 | 1/20/97 | 1/27/97 | |
| 1.1.2 | ____Produce Draft Requirements Document | 8.00d | 1/27/97 | 2/3/97 | 1/27/97 | 2/3/97 | |
| 1.2 | __Clarify stated rqmts | 29.00d | 2/3/97 | 3/3/97 | 2/3/97 | NA | |
| 1.2.1 | ____Get feedback from professor | 8.00d | 2/3/97 | 2/10/97 | 2/3/97 | 2/10/97 | |
| 1.2.2 | ____Update Requirements Document to reflect comments | 8.00d | 2/10/97 | 2/17/97 | 2/10/97 | 2/17/97 | |
| 1.2.3 | ____Get team chop on update | 8.00d | 2/17/97 | 2/24/97 | NA | NA | |
| 1.2.4 | ____Clarify vague and ambiguous requirements | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 1.2.5 | ____Assess technology for supplying reqd S/W | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 1.2.6 | ____Baseline Requirements Document | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 1.3 | __Software Requirements Process Document | 57.00d | 1/27/97 | 3/24/97 | 1/27/97 | NA | |
| 1.3.1 | ____Produce Draft Requirements Process Document | 8.00d | 1/27/97 | 2/3/97 | 1/27/97 | 2/3/97 | |
| 1.3.2 | ____Baseline Requirements Process Document | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 1.4 | __Update SRS for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 1.5 | __Update SRS for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 1.6 | __Produce final SRS for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 2 | MANAGE PROGRAM RISK | 22.00d | 1/20/97 | 2/10/97 | 2/3/97 | NA | |
| 2.1 | __Produce Draft Risk Mitigation Plan (RMP) | 8.00d | 2/3/97 | 2/10/97 | 2/3/97 | 2/10/97 | |
| 2.1.1 | ____Identify Risk Elements, Probabilities and Impacts | 1.00d | 2/3/97 | 2/3/97 | 2/3/97 | 2/3/97 | |
| 2.1.2 | ____Produce Draft RMP | 5.00d | 2/4/97 | 2/8/97 | 2/4/97 | 2/8/97 | |
| 2.1.3 | ____Circulate RMP for comment | 3.00d | 2/8/97 | 2/10/97 | 2/8/97 | 2/10/97 | |
| 2.1.4 | ____Baseline RMP | 1.00d | 2/10/97 | 2/10/97 | 2/10/97 | 2/10/97 | |
| 2.2 | __Conduct Risk Mitigation Activities | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 2.2.1 | ____Risk Monitoring Program | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 2.2.2 | ____Bi-weekly Risk Mitigation Report | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 2.3 | __Update RMP for Preliminary Design Review | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 2.4 | __Update RMP for Critical Design Review | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 2.5 | __Produce final RMP for Functional Acceptance Testing | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 3 | CONDUCT SOFTWARE CONFIGURATION MGMT | 92.00d | 1/27/97 | 4/28/97 | 1/27/97 | NA | |
| 3.1 | __Produce Requirements Management Plan (RMP) | 22.00d | 1/27/97 | 2/17/97 | 1/27/97 | 2/17/97 | |
| 3.1.1 | ____Produce Draft Rqmts Mgmt Plan | 8.00d | 1/27/97 | 2/3/97 | 1/27/97 | 2/3/97 | |
| 3.1.2 | ____Get feedback from professor | 8.00d | 2/3/97 | 2/10/97 | 2/3/97 | 2/10/97 | |
| 3.1.3 | ____Update Baseline Rqmts Mgmt Plan | 8.00d | 2/10/97 | 2/17/97 | 2/10/97 | 2/17/97 | |
| 3.2 | __Update Rqmts Mgmt Plan for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 3.3 | __Update Rqmts Mgmt Plan for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 3.4 | __Produce final Rqmts Mgmt Plan for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 4 | Produce Configuration Management Plan (CMP) | 29.00d | 2/24/97 | 3/24/97 | NA | NA | |
| 4.1 | __Produce Draft Config Mgmt Plan | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 4.2 | __Get feedback from professor | 1.00d | 3/17/97 | 3/17/97 | NA | NA | |
| 4.3 | __Update Config Mgmt Plan | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 5 | Update Config Mgmt Plan for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 6 | Update Config Mgmt Plan for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 7 | Produce final Config Mgmt Plan for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 8 | Conduct Configuration Management Activities | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 8.1 | __Configuration Management Activities | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 8.2 | __Bi-weekly Configuration Management Report | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 9 | CONDUCT SOFTWARE QA/TEST | 99.00d | 1/20/97 | 4/28/97 | NA | NA | |
| 9.1 | __Produce Quality Assurance Plan | 64.00d | 2/24/97 | 4/28/97 | NA | NA | |
| 9.1.1 | ____Produce draft Quality Assurance Plan | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 9.1.2 | ____Get feedback from professor | 1.00d | 3/17/97 | 3/17/97 | NA | NA | |
| 9.1.3 | ____Update Baseline QA Plan | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 9.1.4 | ____Update QA/Test Plan for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 9.1.5 | ____Update QA/Test Plan for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 9.1.6 | ____Produce final QA/Test Plan for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 9.2 | __Conduct Software Test | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 9.3 | __Produce Software Test Report | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 10 | Produce Configuration Management Plan (CMP) | 29.00d | 2/24/97 | 3/24/97 | NA | NA | |
| 10.1 | __Produce Draft Config Mgmt Plan | 8.00d | 2/24/97 | 3/3/97 | NA | NA | |
| 10.2 | __Get feedback from professor | 1.00d | 3/17/97 | 3/17/97 | NA | NA | |
| 10.3 | __Update Config Mgmt Plan | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 11 | Update Config Mgmt Plan for Preliminary Design Review | 8.00d | 3/17/97 | 3/24/97 | NA | NA | |
| 12 | Update Config Mgmt Plan for Critical Design Review | 8.00d | 3/31/97 | 4/7/97 | NA | NA | |
| 13 | Produce final Config Mgmt Plan for Functional Acceptance Testing | 8.00d | 4/21/97 | 4/28/97 | NA | NA | |
| 14 | Conduct Configuration Management Activities | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 14.1 | __Configuration Management Activities | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 14.2 | __Bi-weekly Configuration Management Report | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15 | DEVELOP S/W ARCHITECTURE | 36.00d | 1/20/97 | 2/24/97 | NA | NA | |
| 15.1 | __Produce Software Design Document | 8.00d | 2/17/97 | 2/24/97 | NA | NA | |
| 15.2 | __Update Software Design Document for PDR | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.3 | __Update Software Design Document for CDR | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.4 | __Produce Final Software Design Document | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.5 | __Deliver Initial Software Build | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.5.1 | ____Prototype Links to Software Program Management Sites | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.5.2 | ____Prototype Team Review Section | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.6 | __Deliver 2nd Software Build | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.6.1 | ____Develop WWW Site Layout | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.6.2 | ____Develop "chat room" capability | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.6.3 | ____Develop a minimum of 10 Links to other web sites | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.6.4 | ____Develop section of introductory material | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.6.5 | ____Develop list of suggested keywords and links to other web search engines | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.7 | __Deliver 3rd Software Build | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.7.1 | ____Develop list of or links to a minimum of five tool descriptions | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.7.2 | ____Develop a "levity" page | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.8 | __Deliver Final Software Build | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.8.1 | ____Develop unique materials section for MJY Team papers | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.8.2 | ____Develop bibliography of publications of interest | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 15.8.3 | ____Develop a "lessons learned" page | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 16 | DEVELOP EXTERNAL FUNCTIONAL SPECIFICATION | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 17 | PRODUCE AND DELIVER S/W ITEMS | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 18 | PERFORM PROJECT MGMT FUNCTIONS | 91.00d | 1/20/97 | 4/20/97 | 2/12/97 | NA | |
| 18.1 | __DEFINE PROJECT GOALS & OBJECTIVES | 1.00d | 1/20/97 | 1/20/97 | NA | NA | |
| 18.2 | __SCOPE AND PLAN THE PROJECT | 13.00d | 2/12/97 | 2/24/97 | 2/12/97 | NA | |
| 18.2.1 | ____Define S/W Project Mgmt Process | 6.00d | 2/12/97 | 2/17/97 | 2/12/97 | 2/17/97 | |
| 18.2.2 | ____Define Work Breakdown Structure (WBS) | 6.00d | 2/19/97 | 2/24/97 | NA | NA | |
| 18.2.3 | ____Determine Project Schedule | 6.00d | 2/19/97 | 2/24/97 | NA | NA | |
| 18.2.4 | ____Assign Resources to Tasks | 6.00d | 2/19/97 | 2/24/97 | NA | NA | |
| 18.2.5 | ____Produce MS Project Plan | 6.00d | 2/19/97 | 2/24/97 | NA | NA | |
| 18.2.6 | ____Produce S/W Project Mgmt Plan (SPMP) | 6.00d | 2/19/97 | 2/24/97 | NA | NA | |
| 18.3 | __Administrate the implementation | 56.00d | 2/24/97 | 4/20/97 | NA | NA | |
| 18.3.1 | ____Collect weekly actuals for task completion | 50.00d | 2/24/97 | 4/14/97 | NA | NA | |
| 18.3.2 | ____Update MS Project Plan | 55.00d | 2/25/97 | 4/20/97 | NA | NA | |
| 18.4 | __Evaluate performance and product | 49.00d | 2/25/97 | 4/14/97 | NA | NA | |
| 18.4.1 | ____Conduct bi-weekly project reviews | 49.00d | 2/25/97 | 4/14/97 | NA | NA | |
| 18.4.1.1 | ______Evaluate actual versus projected schedule | 48.00d | 2/25/97 | 4/13/97 | NA | NA | |
| 18.4.1.2 | ______Evaluate actual versus projected cost | 48.00d | 2/25/97 | 4/13/97 | NA | NA | |
| 18.4.1.3 | ______Prepare bi-weekly report | 48.00d | 2/25/97 | 4/13/97 | NA | NA | |
| 18.4.1.4 | ______Brief weekly report | 43.00d | 3/3/97 | 4/14/97 | NA | NA | |