WBS.07.APR.97.1
7 April 1997

Full WBS and Schedule
4/7/97



WBS Name Duration Start Finish Actual Start Actual Finish
1DEFINE S/W RQMTS99.00d1/20/974/28/971/20/97NA
1.1Software Requirements Specification (SRS)99.00d1/20/974/28/971/20/97NA
1.1.1Understand Functional & S/W Rqmts15.00d1/20/972/3/971/20/972/3/97
1.1.1.1Brainstorm Requirements8.00d1/20/971/27/971/20/971/27/97
1.1.1.2Produce Draft SRS8.00d1/27/972/3/971/27/972/3/97
1.1.2Clarify stated rqmts29.00d2/3/973/3/972/3/97NA
1.1.2.1Get feedback from professor8.00d2/3/972/10/972/3/972/10/97
1.1.2.2Update Requirements Document to reflect comments8.00d2/10/972/17/972/10/972/17/97
1.1.2.3Get team chop on update8.00d2/17/972/24/972/17/972/24/97
1.1.2.4Clarify vague and ambiguous requirements8.00d2/24/973/3/972/24/973/3/97
1.1.2.5Assess technology for supplying reqd S/W8.00d2/24/973/3/97NANA
1.1.3Baseline SRS8.00d2/24/973/3/972/24/973/3/97
1.1.4Update SRS for Preliminary Design Review8.00d3/17/973/24/973/17/973/24/97
1.1.5Update SRS for Critical Design Review8.00d3/31/974/7/973/31/974/7/97
1.1.6Produce final SRS for Functional Acceptance Testing8.00d4/21/974/28/97NANA
2MANAGE PROGRAM RISK85.00d2/3/974/28/972/3/97NA
2.1Risk Mitigation Plan85.00d2/3/974/28/972/3/97NA
2.1.1Produce Baseline Risk Mitigation Plan8.00d2/3/972/10/972/3/972/10/97
2.1.1.1Identify Risk Elements, Probabilities and Impacts1.00d2/3/972/3/972/3/972/3/97
2.1.1.2Produce Draft Risk Mitigation Plan5.00d2/4/972/8/972/4/972/8/97
2.1.1.3Circulate Risk Mitigation Plan for comment3.00d2/8/972/10/972/8/972/10/97
2.1.1.4Baseline Risk Mitigation Plan1.00d2/10/972/10/972/10/972/10/97
2.1.2Update Risk Mitigation Plan for Preliminary Design Review8.00d3/17/973/24/97NANA
2.1.3Update Risk Mitigation Plan for Critical Design Review8.00d3/31/974/7/973/31/974/7/97
2.1.4Produce final Risk Mitigation Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
2.2Conduct Risk Mitigation Activities50.00d2/24/974/14/972/24/97NA
2.2.1Evaluate Program Risk Elements48.00d2/24/974/12/972/24/97NA
2.2.2Conduct Risk Mitigation as required48.00d2/24/974/12/97NANA
2.2.3Bi-weekly Risk Mitigation Report to PM43.00d3/3/974/14/973/3/97NA
3CONDUCT SOFTWARE CONFIGURATION MGMT92.00d1/27/974/28/971/27/97NA
3.1Produce Requirements Management Plan92.00d1/27/974/28/971/27/97NA
3.1.1Produce Baseline Rqmts Mgmt Plan22.00d1/27/972/17/971/27/972/17/97
3.1.1.1Produce Draft Rqmt Mgmt Plan8.00d1/27/972/3/971/27/972/3/97
3.1.1.2Get feedback from professor1.00d2/3/972/3/972/3/972/3/97
3.1.1.3Baseline Rqmts Mgmt Plan8.00d2/10/972/17/972/10/972/17/97
3.1.2Update Rqmts Mgmt Plan for Preliminary Design Review8.00d3/17/973/24/973/17/973/24/97
3.1.3Update Rqmts Mgmt Plan for Critical Design Review8.00d3/31/974/7/97NANA
3.1.4Produce final Rqmts Mgmt Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
3.2Produce Software Configuration Management Plan (SCMP)64.00d2/24/974/28/972/24/97NA
3.2.1Produce Baseline Config Mgmt Plan22.00d2/24/973/17/972/24/973/17/97
3.2.1.1Produce Draft SCMP8.00d2/24/973/3/972/24/973/3/97
3.2.1.2Get feedback from professor1.00d3/17/973/17/973/17/973/17/97
3.2.2Update SCMP for Preliminary Design Review (Baseline)8.00d3/17/973/24/973/17/973/24/97
3.2.3Update SCMP for Critical Design Review8.00d3/31/974/7/97NANA
3.2.4Produce final SCMP for Functional Acceptance Testing8.00d4/21/974/28/97NANA
3.3Conduct Configuration Management Activities78.00d2/10/974/28/972/10/97NA
3.3.1Enter Baseline Documentation into Configuration Control78.00d2/10/974/28/972/10/97NA
3.3.1.1Enter SRS into Configuration Control1.00d2/17/972/17/972/17/972/17/97
3.3.1.2Enter S/W Rqmts Proc Doc into Configuration Control1.00d3/24/973/24/973/24/973/24/97
3.3.1.3Enter Risk Mitigation Plan into Configuration Control1.00d2/10/972/10/972/10/972/10/97
3.3.1.4Enter S/W Rqmts Mgmt Plan into Configuration Control1.00d2/17/972/17/972/17/972/17/97
3.3.1.5Enter SCMP into Configuration Control1.00d3/24/973/24/973/24/973/24/97
3.3.1.6Enter QA/Test Plan into Configuration Control1.00d3/24/973/24/973/24/973/24/97
3.3.1.7Enter Software Test Report into Configuration Control1.00d4/28/974/28/97NANA
3.3.2Update Documentation Baseline for PDR1.00d3/24/973/24/973/24/973/24/97
3.3.3Update Documentation Baseline for CDR1.00d4/7/974/7/97NANA
3.3.4Update Documentation Baseline for FAT1.00d4/28/974/28/97NANA
3.3.5Enter Initial Software Baseline into Configuration Control1.00d2/24/972/24/972/24/972/24/97
3.3.6Enter Build 2 into Configuration Control1.00d3/24/973/24/97NANA
3.3.7Enter Build 3 into Configuration Control1.00d4/7/974/7/97NANA
3.3.8Enter Final Build into Configuration Control1.00d4/21/974/21/97NANA
3.3.9Bi-weekly Configuration Mgmt Report to PM43.00d3/3/974/14/97NANA
4DEVELOP S/W ARCHITECTURE92.00d1/27/974/28/971/27/97NA
4.1Produce Software Design Document8.00d2/17/972/24/972/17/972/24/97
4.2Update Software Design Document for PDR8.00d3/17/973/24/97NANA
4.3Update Software Design Document for CDR8.00d3/31/974/7/97NANA
4.4Produce Final Software Design Document8.00d4/21/974/28/97NANA
4.5Deliver Initial Software Build29.00d1/27/972/24/971/27/97NA
4.5.1Prototype Links to Software Program Management Sites28.00d1/27/972/23/971/27/972/23/97
4.5.2Prototype Team Review Section28.00d1/27/972/23/971/27/972/23/97
4.5.3Deliver Initial Build to Software Test1.00d2/24/972/24/97NANA
4.6Deliver 2nd Software Build29.00d2/24/973/24/972/24/97NA
4.6.1Develop WWW Site Layout28.00d2/24/973/23/97NANA
4.6.2Develop "chat room" capability28.00d2/24/973/23/972/24/973/23/97
4.6.3Develop a minimum of 10 Links to other web sites28.00d2/24/973/23/972/24/973/23/97
4.6.4Develop section of introductory material28.00d2/24/973/23/97NANA
4.6.5Develop list of suggested keywords and links to other web search engines28.00d2/24/973/23/97NANA
4.6.6Update previously released sections28.00d2/24/973/23/97NANA
4.6.7Deliver Build 2 to Software Test1.00d3/24/973/24/97NANA
4.7Deliver 3rd Software Build15.00d3/24/974/7/973/24/97NA
4.7.1Develop list of or links to a minimum of five tool descriptions14.00d3/24/974/6/973/24/974/6/97
4.7.2Develop a "levity" page14.00d3/24/974/6/973/24/974/6/97
4.7.3Update previously released sections14.00d3/24/974/6/97NANA
4.7.4Deliver Build 3 to Software Test1.00d4/7/974/7/97NANA
4.8Deliver Final Software Build57.00d2/24/974/21/972/24/97NA
4.8.1Develop unique materials section for MJY Team papers56.00d2/24/974/20/972/24/97NA
4.8.1.1Prepare paper abstract8.00d2/24/973/3/972/24/973/3/97
4.8.1.2Conduct paper research31.00d3/4/974/3/973/4/97NA
4.8.1.3Prepare draft7.00d4/4/974/10/974/4/97NA
4.8.1.4Final paper preparation8.00d4/11/974/18/97NANA
4.8.1.5Post papers to Web site2.00d4/19/974/20/97NANA
4.8.2Develop bibliography of publications of interest36.00d3/3/974/7/97NANA
4.8.3Develop a "lessons learned" page28.00d3/24/974/20/973/24/974/20/97
4.8.4Update previously released sections14.00d4/7/974/20/97NANA
4.8.5Deliver Final Build to Software Test1.00d4/21/974/21/97NANA
5CONDUCT SOFTWARE QA/TEST64.00d2/24/974/28/972/24/97NA
5.1Produce QA/Test Plan64.00d2/24/974/28/972/24/97NA
5.1.1Produce Baseline QA/Test Plan22.00d2/24/973/17/972/24/97NA
5.1.1.1Produce Draft QA/Test Plan8.00d2/24/973/3/972/24/973/3/97
5.1.1.2Get feedback from professor1.00d3/17/973/17/97NANA
5.1.2Update QA/Test Plan for Preliminary Design Review (Baseline)8.00d3/17/973/24/97NANA
5.1.3Update QA/Test Plan for Critical Design Review8.00d3/31/974/7/97NANA
5.1.4Produce final QA/Test Plan for Functional Acceptance Testing8.00d4/21/974/28/97NANA
5.2Conduct Software Test59.00d2/25/974/24/972/25/97NA
5.2.1Test Initial Software Build8.00d2/25/973/4/972/25/97NA
5.2.1.1Conduct Initial Build Test7.00d2/25/973/3/972/25/973/3/97
5.2.1.2Provide Test Status to PM, Developer1.00d3/4/973/4/97NANA
5.2.2Test Build 28.00d3/25/974/1/97NANA
5.2.2.1Conduct Build 2 Test7.00d3/25/973/31/97NANA
5.2.2.2Provide Test Status to PM, Developer1.00d4/1/974/1/97NANA
5.2.3Test Build 38.00d4/8/974/15/97NANA
5.2.3.1Conduct Build 3 Test7.00d4/8/974/14/97NANA
5.2.3.2Provide Test Status to PM, Developer1.00d4/15/974/15/97NANA
5.2.4Test Final Build3.00d4/22/974/24/97NANA
5.3Produce Software Test Report4.00d4/25/974/28/97NANA
5.3.1Compile Software Test Results3.00d4/25/974/27/97NANA
5.3.2Deliver Software Test Report1.00d4/28/974/28/97NANA
6PERFORM PROJECT MGMT FUNCTIONS99.00d1/27/975/5/971/27/97NA
6.1DEFINE PROJECT GOALS & OBJECTIVES8.00d1/27/972/3/971/27/972/3/97
6.2SCOPE AND PLAN THE PROJECT20.00d2/12/973/3/972/12/973/3/97
6.2.1Define S/W Project Mgmt Process6.00d2/12/972/17/972/12/972/17/97
6.2.2Define Work Breakdown Structure (WBS)6.00d2/19/972/24/972/19/972/24/97
6.2.3Determine Project Schedule6.00d2/19/972/24/972/19/972/24/97
6.2.4Produce MS Project Plan6.00d2/19/972/24/972/19/972/24/97
6.2.5Produce S/W Project Mgmt Plan (SPMP)6.00d2/19/972/24/972/19/972/24/97
6.2.6Assign Resources to Tasks7.00d2/25/973/3/972/25/973/3/97
6.3Administrate the implementation56.00d2/24/974/20/972/24/97NA
6.3.1Collect weekly actuals for task completion50.00d2/24/974/14/972/24/97NA
6.3.2Update MS Project Plan55.00d2/25/974/20/972/25/97NA
6.4Evaluate performance and product49.00d2/25/974/14/972/25/97NA
6.4.1Conduct bi-weekly project reviews49.00d2/25/974/14/972/25/97NA
6.4.1.1Evaluate actual versus projected schedule48.00d2/25/974/13/972/25/97NA
6.4.1.2Evaluate actual versus projected cost48.00d2/25/974/13/972/25/97NA
6.4.1.3Prepare bi-weekly report48.00d2/25/974/13/972/25/97NA
6.4.1.4Brief bi-weekly report to PM43.00d3/3/974/14/973/17/97NA
6.5Report Status to Customer/Class36.00d3/17/974/21/973/17/97NA
6.5.1Status Report 1 (Mar 24)8.00d3/17/973/24/973/17/973/24/97
6.5.1.1Prepare Status Report7.00d3/17/973/23/973/17/973/23/97
6.5.1.2Brief Status Report1.00d3/24/973/24/973/24/973/24/97
6.5.2Status Report 2 (Apr 7)8.00d3/31/974/7/973/31/974/7/97
6.5.2.1Prepare Status Report7.00d3/31/974/6/973/31/974/6/97
6.5.2.2Brief Status Report1.00d4/7/974/7/974/7/974/7/97
6.5.3Status Report 3 (Apr 21)8.00d4/14/974/21/97NANA
6.5.3.1Prepare Status Report7.00d4/14/974/20/97NANA
6.5.3.2Brief Status Report1.00d4/21/974/21/97NANA
6.6Terminate the Project1.00d5/5/975/5/97NANA
6.6.1Provide Final Documentation to Dr. Bechtold1.00d5/5/975/5/97NANA
6.6.2Provide Web Site Code to Dr. Bechtold1.00d5/5/975/5/97NANA

Software Project Management / Comments? / Back / Last Updated: April 11, 1997